Project :High density transformation - LIVEIncrease power and cooling without jeopardizing the rest of the installation. |
|
|
|
ClientMohawk Internet Technologies Site :Kahnawake Work period:5 months |
Issue:Existing server room must be transformed to high density in a live environment. Mandate:Feasibility study to increase capacitance and air conditioning. Approach:Performed a feasibility study to install additional servers in the existing cabinets without increasing the room’s area. Technical aspects:Took precise measurements of the existing equipment to the nearest 1/4 of an inch. Results:The client can now install additional servers in the existing cabinets without increasing the room’s area. |
Expertise :Critical Data Centres Services :
Needs Assessment (Electromechanical Expert) |